[ARCHIVED] Park County Road Projects Update - August 8, 2024

Public Works Update Aug 8

Park County Public Works will provide regular updates regarding road projects and maintenance taking place across the county. 

Special Projects

Elkhorn (CR15) 

Project Overview: CR15 also known as the Elkhorn or Elkhorn Road, number of miles, describe why we are doing this 

Updates: The county gave the contractor a final checklist to complete on July 22, 2024. They completed the final checklist and the county signed off on the project on July 31st, 2024. A final packet for the project is being put together to be released to the public and encompasses the entire project scope. 

Timeline: Project successfully completed on July 31, 2024. 

11-Mile Road Reclamation 

Project Overview: Improvements focus on: CR59, CR92, and CR90. Roads will be getting 2 inches of new road base milled in with 2-4 inches of existing chip seal and base. Mag chloride will be mixed in throughout the new and existing material to create a solid road base.  

Updates: CR59, CR92, and CR90 will be getting 2 inches of new road base milled in with 2-4 inches of existing chip seal and base. Mag chloride will be mixed in throughout the new and existing material to create a solid road base. CR59 has been re-graded for proper crown and drainage.  

The contractor has completed roughly 6 miles of CR92 from the Chaparral General Store to the 11-Mile State Park Marina. The contractor is running their reclaimer that mills up the road base about a mile per day and is catching up to road base that was laid last week. They will begin final grading on CR92 and will be applying a top shot of magnesium. 

Timeline: The project began in May 2024 and is scheduled to conclude in September 2024.  

Road Grading and Maintenance Updates by District

County-Wide Work

  • Flood and emergency repair due to storms and runoff 
  • Code Red Call Outs 
  • 78,560 gallons of Mag Chloride 
  • 67,000 tons of gravel placed 
  • 437 road miles graded

District 1 

  • CR58, 60, 68, Burland Ranch, Friendship Ranch, Delwood 
  • Potholes – 115-ton asphalt

District 2

  • CR35,7 ,56 ,33 ,54 ,439, Buffalo subdivision, Arrowhead, Apache, Ute trace, Fitzsimmons 
  • Potholes – 45 tons asphalt

District 3

  • CR23, 53,102, Chaparral Road, 104,59,88 
  • Potholes -147 tons asphalt

District 4  

  • Ranch of the Rockies, Foxtail pines, Coil Placer, 6, Lower 4, 12,14,18 
  • Potholes – 60 tons asphalt

General Updates and Reminders

  • Working hours are 7 a.m. to 7 p.m. Monday to Friday  
  • Signs and construction devices will be present to alert the public to the closures and alternate routes 
  • Construction schedules are weather dependent and subject to change 

Stay Connected! 

Facebook Twitter Email

Other News in Public Works

1041 Draft Regulations Publication announcement

Draft 1041 Regulations Available For Public Review & Comment

Posted on: February 5, 2026 | Last Modified on: February 11, 2026